School Building Project

Updates, Photos and Timelines

November 27, 2016

 

Welcome to Sunrise R-IX School's Building Project site. Please scroll down for photos and construction updates of our school building.  This site will remain updated throughout the building project.

Architect: KRJ

      Project Manager: Jamie

General Contractor: Brockmiller

       Superintendent: Mr. Rick Pyatt

 

CONSTRUCTION SCHEDULE

December 20, 2016 - Awarded Bid to General Contractor: Brockmiller

January-August, 2017 - Construction of 6 additional classrooms, new gym and relocation of Superintendent's office, kindergarten classrooms and 1/2 day PK

July 31, 2017- Tentative completion date

OPENING DAY OF SCHOOL 2017 - August 23, 2017

 

SCHEDULE ADJUSTMENTS

February 20: Sewer Project completed

February 14: Valentine Party parking, someone will be directing area for additional parking on ball field

January 30: fence being built along playground to keep students in pea gravel and in a safety zone from the gym construction area

January 30: parent pick-up should arrive on campus for pick-up between 3:05-3:20 p.m.

January 17: students enter and exit to playground using the 4/5 grade door

January 3: parking is allowed on front fence and back gravel lot

 

CONSTRUCTION UPDATES

 

March 24, 2017: Outdoor classroom trails are all cut in- controlled burn and gravel will come next!

March 24, 2017: more progress for the gym and outdoor classroom clearing

March 20, 2017: Classroom addition! We can envision the building-windows, doors, rooms!

March 17, 2017: Roof going on!

March 10, 2017: gym footings dug

 

March 9, 2017: Beams delivered and installed for classroom addition, footings dug for gym

March 6, 2017: Outdoor classroom trails are being cleared. Getting ready for the controlled burn in April.

 

March 1, 2017: Classroom addition being constructed and finalized color of gym exterior

February 28, 2017: extensive color sample meeting with Building Committee

February 21, 2017: Sewer Project completed

February 21, 2017: Outdoor Classroom clearing continues and planning/timelines consistently updated.

 

 

February 14, 2017: concrete floor poured for MS wing, drilling wells completed 2-16

February 13, 2017: gym progress

 

February 10, 2017: View the progress; new gym, overall, new middle school wing, sewer field

February 9, 2017: gym progress

February 8, 2017: gym ground clearing continues, David meets with vendors in regards to technology within the new additions

February 7, 2017: ground breaking on the gym, wells are continuing to be dug for geothermal, septic progress across the road, and middle school wing classrooms are visible in the ground

 

February 2, 2017: footings poured

January 30, 2017: layout on ground to dig for gym, playground safety fencing installed

 

 

January 26, 2017: pouring concrete footings for middle school addition

     

January 24, 2017: rebar, footings, concrete, oh my!

January 23, 2017: pilings and electric

 

January 17, 2017: footings are being dug

Inserted Image

January 12, 2017

Inserted Image

January 11, 2017: 6 Classrooms ground digging.

Inserted Image

January 9, 2017: Brockmiller brings equipment to campus and begins preliminary site work.

 

 

 

 

 

STIE PLAN:

Inserted Image

Inserted Image

Inserted Image

Inserted Image

 

OTHER RENDERINGS:

A bathroom will be added to the new 1/2 day preschool bathroom. This is Mrs. Brewen's current classroom.

Superintendent Office will be located in current kindergarten rooms. Kindergarten will move to preschool/office wing. The Early Childhood will be PK-K classrooms, located at the office hallway.

 Gym Banners

 

For further information, questions, or concerns, please contact school:
Armand Spurgin, Superintendent
ads@sunrise-r9.org or 636-586-6660